JASON BLEVINS,
PMP
▪ Houston, Texas ▪ bailyblevins@gmail.com ▪ 512.317.5611 mobile ▪
LinkedIn: http://tiny.cc/lfjkh ▪
Education and Certifications
§ BSEE, University of Texas -1995
§ Non-Destructive evaluation, Visual Testing (NDE/NVT) and
Radiography Testing (RT) 2001
§ Micro-station IDDS/ICGS certification 2004
§ AutoCAD certification, Westwood College 2004
§ PMP (Project Management Professional) includes RM (Risk
Management) certification, Villanova University 2005
§ OSHA 30-Hour Card and OSHA 10-Hour Card
SOFTWARE PLATFORMS
Rating = 10 being expert
MS Project9
MS Visio9
MS Office9
AutoCAD (r.14 – MEP 2010)9
SharePoint9
Primavera Engineering & Construction7
Google Sketch Up 3-d Rendering 7
eQuest DOE Energy Modeling
7
Professional
Experience
June 2014 –
June 2015 (Consultant Position)
Boardwalk
Pipeline Partners – References Available
Consulting
engineer/estimator for the Construction and Engineering department of
an NYSE listed natural gas Transmission Company in Houston, Texas. My
responsibility fell within the preparing of cost portion for engineering,
procurement and construction contracts.
This includes
Nationwide:
· Class Change Estimations
· Mandated; Regulatory Change Estimations
· Tap and Riser Engineering/Estimations
· Meter/Regulation Stations Engineering Estimations
· Dehy Stations Estimations
· Compressor Stations Estimations (Turbine/Recip.’s, MCC,
Medium Voltage SW-G, Engineering)
· Pipeline Relocations Engineering/Estimations
· Backhaul Service Expansions Estimations
· Stopple and Bypass’ Engineering/Estimations
January 2011 –
May 2014
Park Cross
Energy, LLC
Park Cross
Energy, LLC developed energy projects in the United States and abroad.
This includes blending fuels such as natural gas, LNG, CNG or [renewable] RDF
with wind and solar power generation to improve the kWh rate case.
Additionally, at Park Cross Energy, LLC we developed several crude oil,
refined petroleum products, and gas and oil exploration opportunities for
world class investment entities nationally and internationally
The goal is to
be innovative in business development, engineering, and execution, with
specific tasks including regulatory and economic issues, constructability,
(including estimations), negotiations with the major manufactures on pricing,
EPC negotiations, financial sustainability (IRR and ROI), and environmental
sustainability.
Responsibilities:
· Business development
· Project programming of:
o
Preliminary Engineering
o
Locating natural gas transmission
lines and designing the preliminary distribution and CAPEX
o
Horizontal and vertical CAPEX
o
Project EPC, work breakdown
structure (WBS)
· Project Financing
o
Packaging of all data for
submittal to financial entities for project funding
o
Pro forma
o
Incentive programs
March 2012 –
November 2012 (CONTRACT Position)
Schneider
Electric (Contracted through Park Cross Energy, LLC)
As a Contract Project
Manager for the joint US Navy/ Schneider Electric Advance Metering
Infrastructure (AMI) in the NAVFAC FE region for the naval bases in
Japan:
· On-site, in Japan’s Yokosuka Naval Base and Atsugi, Naval
Air Facility, conduct kickoff-meetings for the AMI program
· Management of this project is from my virtual/home office
· Manage the preliminary design process as it pertains to
the solicitation of bids from, internal engineering resources, external
installation contractors and other suppliers.
· Manage all budgets and scope of work for Yokosuka and
Atsugi naval bases (US$15,000,000.00+)
· Single point of contact and interface for the US Navy and
Schneider Electric
· Ensure all project progress milestones are met:
engineering, procurement and construction
· Ensure all milestone payments are invoiced and accounted
for, in the contractual payment schedule
· Ensure all documentation: contract changes, delay/control
notifications, change management issues, etc.
· Ensure all project resources have the ability to gain
access to the military installation via government’s Invitational Travel
Orders, CAC and SOFA process
The Advanced
Metering Infrastructure (AMI) for Naval Facilities Engineering Command Far
East, Japan. The work performed provides for the design, purchase of
equipment, installation of equipment and systems, build, documentation, and
testing of an AMI system for the electricity, water, and steam metering.
August 2009 –
January 2011
RobustEnergy –
VP of Project Manager (Start-up Company July 2009)
· Custom project management process defined, created, and
implemented for the start-up company
· Initiated ETRM platform (Energy Trading and Risk
Management)
· Provide technical assistance to customers on combined heat
and power (CHP) and the benefits of
· Created presentations in PowerPoint and bound hard copy
for City and State officials along with private end-users/owners for US,
China, Turkey,
o
Initiated and performed “lunch and
learns” for the likes of PSP, Getting and Associates, and Zachary
o
Presentations for development with
City Council and Government officials in the US and abroad
· Engaged in power purchase agreements (PPA) with utilities
or retail electric providers (REP)
· Utilizing resources assigned and procured services of the
general contractor, electrical/mechanical contractors, controls contractor,
engineering contractors, equipment suppliers, etc.
· Equipment selection from major mechanical down to lv/mv
switchgear and controls systems
· Provided all drawings associated with conceptual engineering,
this included site layout, electrical one-lines, and P&ID’s in AutoCAD
MEP 2010
· Provided process flow diagrams (PFD)
· Adhered to al Public Utility Council of Texas (PUCT),
ERCOT, SPP zones and territories for exporting power to the grid
· Provide work breakdown structures (WBS) for conceptually
engineered projects and preliminary schedule utilizing MS Project and
Primavera P6
· Provide the preliminary scope of work (SOW) for RFP
process to vendors (all disciplines and inclusive of engineering services)
September 2007
– August 2009 (CONTRACT Position)
Turbine Air
Systems - EPC Project Manager (~5MW CHP – 1350 TR)
· Custom Engineering, Procurement and Construction process
creation for the company due to this project being the first project outside
the ISO manufacturing process for TAS.
· Provide assistance to the Commercial Support Department in
providing construction cost interface from the Installation Contractor.
· Manage the preliminary design process as it pertains to
the solicitation of bids from Installation Contractors and other suppliers.
· Use of Solar Turbines efficiency program to determine the
efficiency calculation n of the turbine incorporated with the Trane Chillers
performance software to
· Provide guidance to Sales and Commercial Support in the
fine-tuning of the project scope and pre-award budgets.
· As the Project Manager, I am utilized in the contract
pre-award stage to ensure clear definitions of project scope of work,
schedule and appropriate budget control.
· Participate in proposal clarification meetings held
between the Company and prospective clients as needed.
· Primary focal point for project written and verbal
communication between the Company and the customer.
· Responsible for internal distribution of all project
related documentation for review and revisions as required.
· Interact with suppliers on all scope, cost, contractual,
and schedule issues. Responsible for orchestrating the internal
resources needed in support of project execution (i.e. Production Systems
Inventory, Document Control, QA/QC, Fabrication, Engineering, Field Service
and After Market)
· Conduct weekly, bi-weekly and monthly individual project
budget reviews and prepare forecasts to completion. Budget performance is reviewed
monthly on a 1-on-1 basis w/ the CFO and Finance
· Solicit and review project specific accounting data for
budget analysis and forecasting purposes.
· Assume full Customer interface for construction issues.
· Field all inquiries from the Customer and the Customer’s
contractor
· Assist in Accounting in invoice collections, attempting to
maximize our leverage between payments to our installation contractors and
suppliers, and invoicing to our customer.
· Protects against creep of the project scope through budget
awareness and the use of change orders.
June 2006 –
August 2007, Hilliard Energy (CONTRACT Position)
Sr. Electrical
Engineer (Wind Turbine Development and Transmission)
§ Configuration/calculations of ATC using manual
calculations and software (Power World ATC/OPF)
§ Agency interface with ERCOT, SPP, etc.
§ Interface with infrastructure owners for information
determining upgrades to existing systems
§ Export potential of transmission lines (69, 138, 345kV,
etc.)
§ Customer customizing of determinable power for residential
turbines (10 -50kW) “on grid” or net-metering
§ Interconnection feasibilities and/or research
§ Review of metrological data for determination of planned
sites
§ Review of environmental data for impact studies of planned
sites
March 2006 –
May 2006, Flow Jamaica (Contract)
Design
Engineer (Jamaica, Bahamas, and Trinidad)
§ Created design specs for Fiber Optic, RF and Hybrid
operations for a startup company (triple-play), Flow Jamaica, Cable Bahamas
and the start up in Trinidad.
§ Input of design specifications and limits into Load Data
and AutoCAD (2006) application for RF design
§ Created installation manual for OSP aerial and OSP buried
for company.
§ Avaya protocol and specifications for PBX installation
July 2003 –
January 2006, Ameriss Corporation, New York City and Dallas, TX
Mid - Atlantic
Project Manager (Verizon)
§ Wrote/responded RFP for Mid-Atlantic on behalf of
corporate
§ Created and issued capital projections for each assigned
OSP project(s)
§ Reviewed and coordinated due diligence of each OSP
project(s)
§ Corporate P&L responsibilities for region
§ OSP Engineering process written and approved by customer
§ Milestone/Timeline management of CAD Drafting Department
(Micro-station and AutoCAD)
§ Milestone/Timeline management of Engineering Department
§ Development of satellite office model for ease of opening
offices
§ Maintained reporting structure and development of such for
“customer” and “corporate”
§ Twice weekly teleconference with Suzhou, China
manufacturing plant
§ On-site milestone/schedule meeting 10 days every quarter
for our Suzhou, China manufacturing plant
September 2001
– May 2003 AES, Dominican Republic (CONTRACT Position)
Design
Engineer – Two (2) 350MW LNG plants w/ 65 KM of 24” pipeline
Construction
Project Manager – Two (2) 350MW LNG plants w/ 65 KM of 24” pipeline
1995 – August
2001 AT&T New York City
SONET Design
Engineer